Facilities

  • Road

    Cast concrete 25 cm thickness.
    Main road          : 32–56 m ROW (Right of Way)
    Secondary road : 15–24 m ROW (Right of Way)

  • Drainage

    Reinforced concrete, open system.

  • Electricity

    Supplied by PT. PLN (Persero), The-State-Owned Electricity Company.
    Capacity     : >500 MVA
    Occupied    : 196 MVA
    Underground cable network.

  • Water Treatment Plant

    Supplied by PT. Multi Tirta Mandiri, privately-owned company by PT. Modernland Realty, Tbk.
    Capacity     : 1,296,000 m3/month
    Occupied   : 259,200m3/month

  • Natural Gas

    Supplied by PT. PGN (Persero), Tbk., The State Owned Gas Company

  • Telecommunication

    Supplied by PT. Telkom Indonesia, Tbk.
    Capacity    : 5,000 connection lines
    Occupied  : 4,000 connection lines

  • Internet

    Supplied by PT. Telkom Indonesia, Tbk. and PT. Indosat, Tbk.